Upon notification to a property owner that an activity is causing
or contributing to violations of the Town's MS4 SPDES permit,
that property owner shall take all reasonable actions, within 30 days
of written notification, to correct such activities such that the
activity no longer causes or contributes to violations of the municipality's
MS4 SPDES permit authorization. If special conditions warrant a delay
in corrective action, a request for an extension of time must be made
in writing to the SMO. The granting of an extension shall not be construed
as permission to violate conditions set forth in this chapter, nor
shall it be used to set precedent for future extension requests.